On 25 November 2026 the Federal Council sent Parliament a partial revision of the Telecommunications Act that changes how mobile antennas are cleared for use. Radiation-protection compliance would leave the building-permit process and move into a new operating authorisation. Radiation limits would not change. Parliament should adopt that core design, then close the gaps that could blunt it.
The problem is procedural
In 2024 the Federal Supreme Court ruled in several cases that almost every antenna modification needs an ordinary building-permit procedure. According to the Federal Office of Communications (OFCOM) fact sheet, this covers technical changes with no visible effect, and even changes that lower exposure. It complicates the commissioning of several hundred modified, replaced or new antennas each year.
The backlog risk was visible early. Netzwoche reported in 2024 that Swisscom alone had to file 1,300 retroactive building applications. The telecom industry association asut says procedures facing objections now take two to three years, sometimes much longer. That is an interested party's figure, but a process measured in years is plainly ill-suited to equipment that needs continual adjustment.
What the bill changes
Under the draft and its explanatory dispatch, published in provisional form:
- Operators need an operating authorisation before first commissioning an antenna, or recommissioning it after a modification. A competent body, such as a cantonal radiation office, has two months to check compliance.
- New installations and non-minor structural changes, such as new foundations or a taller mast, still need a building permit.
- Swapping antenna units, even for slightly different sizes, or activating adaptive mode can need only the operating authorisation, where construction and planning effects are nil or minor.
- Operators must run a certified quality-assurance system and periodically report deviations from authorised parameters.
- Broken installations can in exceptional cases be restored before authorisation, where an overriding public interest requires it.
This puts each question before the body equipped to answer it. Whether a mast suits a streetscape is a planning judgement. Whether transmission parameters respect legal exposure limits is a technical test. The dispatch notes that compliant operators are entitled to authorisation, with no discretionary balancing of interests. It also cites Germany, where the Federal Network Agency checks limit values through its own site certificates.
The case against deserves an answer
The strongest objection concerns remedies. Residents can now object to a building application before a decision is made. In their March 2026 consultation response, the Greens warned that replacing a free, preventive objection with a later and potentially costly appeal, without suspensive effect, could leave unlawful installations running for years before a court rules. They also said some cantons lack the resources to check site data and measurements. Environmental and health organisations, and some communes and cities, likewise opposed the bill.
The concern is serious, and the dispatch confirms that prior objection disappears. What remains is still substantial. Each authorisation must be published with the verified site data sheet, and affected parties have 30 days to appeal. An appeal body can grant suspensive effect on request where a breach of radiation rules appears obvious or particularly serious; either ground is enough. Because settings can be adjusted without demolishing anything, an exceedance is also easier to correct than a faulty building. The government argues that the Constitution guarantees access to a court, but neither a prior objection stage nor automatic suspension.
On balance the trade is proportionate. Automatic suspension lets the mere filing of a challenge stop a lawful upgrade. A targeted power to suspend protects people where the legal case is strong.
Where Parliament should press
The two-month deadline is softer than it sounds. The dispatch calls it a procedural target: if an authority misses it, authorisation is not deemed granted, though operators can use general remedies against undue delay. If a data sheet is incomplete, wrong or non-compliant, the two months restart once the corrected version arrives.
Tacit approval would be the wrong fix, because a radiation check should actually happen. Transparency is the better one. Parliament should require each competent authority to report annually how long decisions take from first filing, how often the clock restarted, and how many cases ran past two months. It should also ask for prompt completeness checks, so that a missing field does not surface in week eight.
Capacity needs testing too. The government expects cantons' workload to stay roughly the same or probably fall, with no extra staff. Those figures would show whether that holds.
Publication deserves similar care. OFCOM's antenna data will appear on the federal geoportal, but authorisations will be published under cantonal or federal procedural rules, and a central federal publication platform was rejected. With a 30-day appeal window, notices should be easy to find. Common data fields and links from the geoportal would be a modest safeguard.
Finally, expectations should be realistic. New sites will still need a building permit and then an operating authorisation, in practice one after the other. This bill mainly helps maintain and modernise existing networks. Closing coverage gaps will still depend on cantons and communes deciding siting applications promptly. That limit is no reason to delay a reform that keeps health standards intact and matches procedure to the risk being assessed.