On 25 November 2026 the Federal Council sent parliament a dispatch amending the Telecommunications Act (FMG). Radiation-protection checks for modernised mobile antennas would leave the building permit process and move into a separate operating permit. Cantonal or municipal specialist offices would have two months to review compliance. New installations and larger structural changes still need a building permit, and the radiation limits stay as they are. Parliament now decides.
The strongest case against the reform
Switzerland's mobile siting rules rest on public trust, and that trust is the point of the system. Today the same permit process that decides whether a mast fits the neighbourhood also tests whether it complies with radiation limits, and neighbours can object to both. BAKOM's 5G FAQ says cantons and municipalities "check whether the antennas comply with the radiation limit values" as part of permitting. Critics, including the Greens in their consultation response, want the current level of protection against non-ionising radiation kept and fear that a separate permit will thin out scrutiny. If appeals no longer stop an antenna from switching on, residents may lose their one effective lever.
That concern is legitimate and deserves a serious answer. The answer is in the design, not in the status quo.
What actually changes
The Swiss limits are already among the strictest in the region. BAKOM states that the installation limit values were not relaxed for 5G and describes them as ten times lower than those of neighbouring countries. The dispatch does not touch them. What moves is the sequencing. Per the hook, the specialist office gets a fixed two-month window, an operating permit that can still be appealed, and suspension of operation on appeal only in justified exceptions.
The December 2025 consultation draft, as reported by pctipp, added two further elements. Operators would have to run a quality assurance system that checks and maintains compliance with limit values during operation. Antenna data from BAKOM's database would be easier to access. The dispatch now goes a step further by putting operating data on the federal geoportal. This is the part critics should weigh most heavily. Today, compliance is a one-time paper check at the permit stage. The reform adds an ongoing duty on operators and puts the data in public view, so residents and journalists can check it independently.
Why the status quo is the real cost
The case for reform is about delay. A Ground News summary of the original reporting on the consultation says installing or upgrading an antenna currently takes more than a year on average. That figure comes from secondary reporting and should be read as indicative, not as an official statistic. Still, the direction is plausible, because a modernisation that only swaps equipment on an existing mast currently runs through a procedure designed for new construction.
A year of waiting for a hardware swap has real costs. Network upgrades improve capacity and efficiency, and the delay falls on the people the permit system is meant to serve: commuters on congested cells and rural users waiting for better coverage. It also does nothing for radiation protection, because the limit is the same before and after the swap. A process that spends its time on questions unrelated to the limit protects no one.
The cantons are the hinge
The reform lands on the cantons, which enforce the radiation rules. The Solothurn cantonal government, responding to the consultation, backed the decoupling in principle: "Der Strahlenschutz soll vom eigentlichen Baubewilligungsverfahren entkoppelt werden." It expects more work at cantonal level and says it is ready to accept it, because centralising the environmental review at the cantonal NIS specialist office should bring clarity, efficiency and legal certainty and relieve municipalities. It also attached conditions: a clear federal legal basis so that changed use of existing antennas no longer needs a building permit, and consistent sanctions for operators who violate federal environmental law, backed by a high fine framework.
Those conditions point to where parliament should focus. A two-month deadline works only if cantonal offices are staffed to meet it. If the deadline lapses, parliament should decide what happens. A silent approval would weaken protection, while an open-ended wait would recreate the delay. Parliament should say which, and fund the offices accordingly.
What parliament should keep and fix
Three points matter most.
- Keep the limits untouched. The political bargain only holds if radiation values stay where they are. Any attempt to loosen them in committee should be rejected, because it would turn a procedural reform into a protection fight and likely sink it.
- Keep the appeal right, and keep suspension narrow but real. An operating permit that can be appealed preserves access to courts. Suspending operation only in justified exceptions is a reasonable default for a measure that is checked before the permit is issued. Parliament should define "justified" tightly enough to be predictable, for example by tying it to a credible claim that a limit would be exceeded.
- Make the transparency real. Publishing operating data on the federal geoportal is the best answer to critics. It should cover data on actual operation, not only design values, and be machine-readable, so independent checking is easy.
The dispatch is a useful corrective to a habit common in European telecom regulation: treating every procedural step as a safety measure. Switzerland has set a strict limit, and that is a legitimate choice. Enforcing it through a faster, more focused process, with ongoing operator duties and public data, is a better way to deliver the same protection. Whether it survives parliament will depend on whether lawmakers keep the two promises that make it credible: no change to the limits, and real accountability for operators once the antennas are running.