The case for Eskom's offer
Eskom's pitch to hyperscalers has a real logic. The utility has spare capacity and a heavy debt load, which the Financial Times reported at about R359 billion after a R254 billion government relief package. Its chair, Mteto Nyati, said of the spare capacity: "We've got this power that we cannot sell." Selling roughly 6 GW to Amazon, Microsoft and Google would put idle plant to work and could ease pressure on tariffs. A state utility that wants to serve a growing, well-funded customer class is a sensible thing to want.
That case holds as far as it goes. But what Teraco announced this month shows a different route to the same goal, and it is the route more countries should copy.
What Teraco actually showed
On 17 November 2026 Teraco, a Digital Realty company, said wind power from its first contracted independent power producer has reached its Cape Town data centres since September 2026. The power moved across Eskom's network and municipal grids. Teraco is working with Eskom, the City of Ekurhuleni and the City of Cape Town on the supply arrangements. Its self-built 120 MW Sediba solar plant in the Free State is due for grid energisation in December 2026, with hot commissioning and Eskom compliance testing in early 2027.
The notable claim is about sequence. Teraco says building Sediba "helped unlock the wheeling frameworks and tariffs that made our wind PPAs possible." That is the company's own account and it names no regulator. Even so, it fits the public record. NERSA, South Africa's electricity regulator, lists its Regulatory Rules on Network Charges for Third-Party Transportation of Energy, with reasons for decision dated 8 April 2025. Those rules set the price of using someone else's wires, which is the thing a wheeling deal depends on.
A caveat on the money: the release describes a R3.5 billion capital commitment to a self-build solar programme starting with Sediba. A project fact box in the same release gives Sediba itself a cost of R2.25 billion. These figures are consistent only if Sediba is the first part of a larger programme, which the release does not spell out.
The constraint is the wires
Teraco does not want Eskom's surplus. Its head of sustainability, Bryce Allan, told TechCentral in August that the constraint is "grid access and frictionless wheeling," and added that "Eskom plays an important role and will continue to supply us with physical energy." He also said the wheeling path is open to Eskom Green. So the real policy question is whether any generator, including Eskom's own, can sell to any large customer at a published and predictable network charge.
The scale of the opportunity is also uncertain. Allan put the current generation surplus at "between 3-6GW." Eskom's headline figure is the top of that range. Teraco itself runs roughly 189 MW of critical capacity, according to the same TechCentral report. A 6 GW surplus is far larger than South Africa's current data centre load. Matching the two will take years, and the data centre side may not materialise at the pace Eskom hopes.
Why this matters beyond South Africa
Data centre power demand is now a global planning problem. The IEA's Energy and AI report says data centres used about 415 TWh in 2024, about 1.5% of global electricity. It projects demand to roughly double to about 945 TWh by 2030, just under 3% of global use. Every grid operator and regulator will face this question: do you build bespoke deals for each large customer, or do you open the network?
Bespoke deals are attractive to politicians because they produce announcements. They also carry costs. A negotiated hyperscaler tariff can bake in subsidies that other ratepayers cover. The same TechCentral piece notes that any new customer tariff needs NERSA approval. It can lock in a single supplier, and it makes the customer a bargaining chip rather than a participant in a market. Open-access wheeling does the opposite. Many generators compete, the customer picks its supplier, and the network owner earns a regulated charge for the use of its wires.
There is also a resilience argument that the EFF made on 18 November in a post on outages at large cloud providers: when a few firms dominate critical infrastructure, one failure spreads. Power supply follows the same logic. A data centre fed by several independent producers, with the utility still supplying the physical backstop, is more robust than one tied to a single contract.
What regulators should do
Proportionate policy here is not complicated, and it does not require heavy new rules on data centres:
- Publish wheeling charges and keep them stable. Investors in generation and in data centres both need to price the network charge before they commit capital. NERSA's 2025 network-charge rules are a good start. The test is whether municipalities apply them consistently.
- Fix interfaces between the national utility and municipal networks. Teraco's power crossed Eskom's network and two city grids. Each hand-off is a place where a project can stall.
- Let Eskom compete, not gatekeep. If Eskom Green can use the same wheeling path, the utility can sell its surplus on equal terms. That is a better test of demand than a single mega-deal.
- Avoid data-centre-specific mandates. Rules that demand renewable sourcing or special tariffs for one customer class invite litigation and distort siting. General open-access rules serve every large consumer.
The record so far is a single supply route and a plant that has not yet been energised, so it would be premature to call this a model. But the direction is right. South Africa's data centre sector can grow faster on a network that any generator can use at a known price than on a surplus that one state utility is trying to sell. Other regulators facing the same demand curve should take note.