In a letter dated 3 November, according to Moneycontrol's reporting, the Broadband India Forum (BIF) asked the Department of Telecommunications (DoT) for a subsea resilience package. It includes an India-flagged repair ship, repair-vessel approvals within seven days, and either pre-approved landing sites along the mainland coast or a 30-day deadline for new stations and cable projects. BIF also wants four to five times more cable landings, ten times more landing stations, passive landing infrastructure open to firms without international long-distance (ILD) licences, and a lawful-interception exemption for international transit traffic.
These are industry proposals, and no DoT acceptance of the package has been reported. The department should start with the reforms that cut delay and widen investment through rule changes.
Put a clock on repairs
India's repair problem is serious. The Telecom Regulatory Authority of India (TRAI), in its June 2023 recommendations on cable landing, reproduced a stakeholder's figures showing average response times in Indian waters of three to five months under one maintenance arrangement and four to five under another. BIF's package, as reported, puts foreign ships' mobilisation at 10 to 12 days and full restoration at three to five months. The measures differ, but the gap suggests that sailing time is only part of the story.
Paperwork is a plausible share of the rest. TRAI found that landing, laying and repair work needs clearances from several agencies, with no defined turnaround time. Stakeholders named the defence and home ministries, shipping and customs authorities, and environmental and coastal regulators.
An ITU advisory body on cable resilience recommends published permitting timelines, pre-clearance of ships and crews, expeditious emergency repairs and, where national law permits, a single government point of contact. DoT has been developing a single-window portal for repair clearances; August reporting gave March 2027 as a tentative implementation target. A portal without binding deadlines would merely digitise the queue.
Seven days should be the outer limit. Contracted vessels and crews should hold standing clearance, renewed in advance, so that a fault triggers notification rather than a fresh round of applications. Security agencies need power to stop a specific vessel for stated reasons. Routine approvals should be deemed granted when the clock expires.
A ship without a flag mandate
The case for an Indian ship is strong. A vessel based at home could arrive sooner, face fewer permit and customs hurdles, and build scarce skills. TRAI accepted much of this, noting that no repair vessel, Indian or foreign, was then stationed near Indian territorial waters.
It also warned that a flag alone would not solve delays, and that deploying and running such a ship would be very costly. It recommended a government-industry committee to study viability and incentives, cable depots on both coasts, and persuading existing operators to base and reflag vessels in India. Crucially, its view was that an Indian ship should be an added option, with no flag restrictions on repair work.
DoT should hold that line. If public money, including from the Digital Bharat Nidhi as BIF suggests, fills a viability gap, it should be awarded competitively against response-time guarantees. Cable owners must remain free to call whichever qualified ship can get there first.
Make 30 days achievable
Concentration is the second risk. A Takshashila Institution paper published in July says at least 13 cables land within a six-kilometre stretch of Versova beach in Mumbai.
Pre-approved sites are the better of BIF's two options. TRAI's survey of foreign practice found that Australia's regulator had 25 business days, extendable to 35, to decide permits inside cable protection zones, against 60, extendable to 90, outside them. Singapore steers new systems to designated landing sites, though some of its approval steps still took months. Speed comes from settling land, coastal and security questions before an applicant arrives. A 30-day promise without that groundwork is likely to slip.
The four-to-fivefold and tenfold targets are useful signals of ambition, but they should not become quotas. The state's job is to make sites available and let demand decide how many get built.
Open ownership, assign duties
BIF argues that tying landing infrastructure to ILD holders limits competition. Letting infrastructure investors own passive assets could bring in new capital. The worry that nobody will answer for a sensitive facility is legitimate, so passive owners should face security vetting and fair-access duties, while licensed operators of the active equipment keep traffic obligations. The 2026 authorisation rules already let authorised entities place terminal equipment at separate landing points of presence. According to Khaitan & Co, they also dropped a draft equal-access mandate for station owners, leaving general non-discrimination conditions and TRAI rules to apply.
Write a narrow transit rule
Security agencies can fairly argue that traffic crossing Indian facilities should stay visible, because a loose "transit" label could hide domestic communications. Yet imposing interception infrastructure on data that neither starts nor ends in India raises cost and privacy concerns, and gives international carriers a reason to route elsewhere.
TRAI recommended explicitly permitting such traffic to pass between cables, with routing details disclosed to authorities. Its recommendation did not grant the interception exemption some stakeholders sought. Khaitan's summary says the 2026 rules retain extensive interception obligations, including for international long-distance providers.
DoT should grant a defined exemption for verifiably separated transit traffic, backed by routing disclosure, audits and penalties for mislabelling. Domestic traffic would stay under existing law. Together with repair clocks and pre-cleared sites, that would give investors rules they can price while India tests whether its own ship pays.